Salko Electrical – Building Services Phase 1 & Phase 2

Whitby, UK (North Yorkshire)

Project Background

Woodsmith Project has been called the biggest mining project in Britain in decades. Anglo American currently develops a polyhalite mine in a sensitive local landscape, the North York National Park. To receive permission for mine development the company has to abide by strict environmental limits, which govern all activities during the construction phase.

To reduce the visual impact of the mine shaft the head frames will be sunk below ground and surface buildings will be kept to a minimum. The project area contains the largest, highest grade resource of polyhalite worldwide. Once the mine is at full operation, a capacity of up to 20 million tonnes per annum is awaited.

The Objective

Provide Electrical solutions and infrastructure for systems critical to shaft sinking activities. The two main shafts at Woodsmith Project will be the deepest commercial mineshafts in the U.K. and Europe. The production shaft will reach a depth of 1594 meters, and the service shaft will reach 1565 meters, both with a diameter of 6.75 meters

Salko Solution

Salko Project managed the supply (including ordering, logistics, expediting, receiving, and site laydown) and installation of;

All electrical distribution components and equipment in accordance to the specifications/criteria by the client requirements and reviewed changes.

The electrical system was supplied at 400V from Transformer 1813-TX-001 (11kV-400/230V).
Transformer 1813-TX-001 is covered under WS Production Shaft Winder Electrical Equipment
Installation Scope of Work.

Design and supply;

  • 1813-DB-002 – Electrical Room 400/230V Distribution Board;
  • 1813-DB-003 – Cellar Area 400/230V Distribution Board;
  • 1813-DB-004 – First Floor 400/230V Distribution Board;
  • 1813-DB-005 – Hoist Area 400/230V Distribution Board;
  • 1813-DB-006 – Fore Collar 400/230V Distribution Board #1; and
  • 1813-DB-007 – Collar Area 400/230V Distribution Board.
  • 1913-DB-016 – First Floor Area 400/230V Distribution Board #2;
  • 1913-DB-017 – Collar Area 400/230V Distribution Board #3;
  • 7411-PLC-1000-PLC panel
  • 7411-PLC-2000-PLC panel
  • 7411-PLC-4000-PLC panel
  • 7411-RIO-0001-RIO panel
  • 7411-RIO-0002-RIO panel
  • 7411-RIO-0003-RIO panel
  • 7411-RIO-0004-RIO panel
  • 7411-RIO-0005-RIO panel
  • 7411-RIO-0006-RIO panel
  • 7411-RIO-0007-RIO panel
  • 7411-NWT-0001 Network PLC
  • 7411-HMI-001-HMI panel
  • 7411-HMI-002-HMI panel
  • 7411-HMI-003-HMI panel
  • 7411-HMI-004-HMI panel

Executed Scope;

  • Installation of Primary containment , secondary containment design and installation.
  • Supply or Fabrication and installation of all stands, mounts, supports, or fixtures required for the adequate support and installation of any electrical equipment including LV transformers, 400V and 690V distribution panels, control stations, local isolation switches, socket outlets, welding outlets, construction power panels.
  • Installation of Earthing of the cable tray system , site plant equipment and the area ground earthing grid.
  • Small power requirements /Lighting as detailed on the client Single Line Drawing .
  • Installation of 110V/ 400/230V distribution panels.
  • Testing and Termination of all cables.
  • Tagging of all cables as identified in the cable schedule.
  • Bonding of all equipment to the Collar House/Headframe earthing grid.

Salko Key Data:

Country, Location: United Kingdom, Whitby, North Yorkshire
Project Execution: June 2021 – Aug 2022
Application: Project Pre – Shaft Sinking
Key Project Activities: Procurement, Logistics, Expediting, Installation, Commissioning
Installed Cable: 7483.67 mtrs