Project Background

The end client engaged with Salko to design, procure, manufacture, and deliver x50 EGD1 liner plates for their EGD1 Insulation upgrades on GT26 Exhausts in 2023 and 2024.

Objective

The objective for the client is to have 5 fully fabricated sets (50 liner plates in total) to install during their C-Inspections in 2023 and 2024.

Salko Solution

Salko is supplying the liner plates fully fabricated, along with a comprehensive quality pack during the handover.

The project entailed:

  • Production of liner plate fabrication drawings
  • Procurement of material (321 stainless steel)
  • Laser cutting, forming, and rolling to fabrications drawings.
  • Fabrication of liner plates in three sections – including welding and NDT
  • Fabrication of support and storage frames
  • Delivery to site
  • Handover of Quality Documentation

Salko Key Data:

Country, Location: Salko UK Workshop, UK
Project Execution: Dec – March 2023
Application: Energy
Key Project Activities Design, Procurement, Fabrication, QA

 